2.7 Questionnaire

Question

What are the seven principles?

continued business justification, learn from others, defined roles and responsibilities, manage by stages, manage by exception, focus on products, tailored to suit the project environment

continued business justification, learn from experience, defined roles and responsibilities, manage by stages, manage by exception, focus on products, tailored to suit the project environment

continued business justification, learn from experience, defined roles and responsibilities, manage by stages, manage by rules, focus on products, tailored to suit the project environment


Question

What are the seven themes?

Business case, Learn from experience, Quality, Plans, Risk, Change, Progress

Business case, Organization, Quality, Manage by stages, Risk, Change, Progress

Business case, Organization, Quality, Plans, Risk, Change, Progress


Question

What are the seven processes?

Starting up a product, Directing a project, Initiating a project, Controlling a Stage, Managing stage boundaries, Managing product delivery, Closing a project

Starting up a project, Directing a project, Initiating a project, Controlling a Stage, Managing stage boundaries, Managing product delivery, Closing a project

Starting up a project, Directing a project, Initiating a project, Controlling a Stage, Closing stage boundaries, Managing product delivery, Closing a project


Question

What kind of plans defined by Prince2?

Project Plan, Project Manager's Plan, Team Plan

Project Plan, Stage Plan, Team Plan

Project Plan, Stage Plan, Work Package Plan


Question

What kind of documents support monitoring the progress?

Checkpoint report

Highlight report

Exception report



Question

What kind of tolerances defined by PRINCE2?

Work Package Tolerances, Stage tolerances, Project tolerances

Team Tolerances, Project Manager tolerances, Board tolerances

Team Tolerances, Stage tolerances, Project tolerances


Question

What should be continuously justified?

Change

Business Case

Risk


Question

Which principle supports the wide applicability and adaptability of PRINCE2?

Tailored to suit the project environment

Focus on products

Manage by exception


Question

Project Board consists of:

any number of executives, any number of Senior Manager, any number of Senior Supplier

one executive, any number of Senior User, any number of Senior Supplier

one director, any number of Senior Manager, any number of Senior Supplier


Question

Team leaders report their progress regulary in:

Highlight reports

Checkpoint reports